The Vario 1970mm BK-117 Build
Tail Spar and the Plywood Framing
As promised, the pictures showing the tail spar...
Through the slot...
Twist up into place...
Install horizontal stabs...
Actually worked better than expected. Rigid and straight.
Also spent some time working on the skid rail mounts.
The laser cutting shop called and my plywood framing was ready.
It turned out amazingly well except a few pieces had a bit of charcoal as the 8 ply 4mm proved difficult for their laser to get through, but nothing a little sanding won't fix.
A trial fit of the floor boards and frames showed the planning was well worth the effort as everything fit like a glove. Just a few minor mods.
Mocked up the mechanics rack topside...
This is the tray/tub that holds the mechanics, dropping them just below the roof line.
Assembled into the roof plate...
With everything lined up I started gluing the main frames into place. These had to be properly aligned with the landing skid recesses and the overhead plate as well as ensuring the floorboards sat properly in place. This is just a 'tack' job to orient everything. Once they've set everything will be easier to set into place and then I'll do a final Hysol job.
Rob M.