Back to Build Stories
Build Story

Vario 1:4 Scale MD500E Build

Chapter 20 of 50

Gluing Up the Struts and Skids

Mar 18, 2020

March 18, 2020

Took the leap and went about gluing up the struts and skids.

Running wire for the nav lights.

Stuffing in the "marshmallows."

You can see a 'marshmallow' in the original hole. I had to re-drill a new hole for the rear skid for both scale accuracy and symmetry.

High tech alignment apparatus.

So far so good.

March 19, 2020

I meant to sand off the Vario front strut fairing detail before I put in the tubes (as I did with the rear but forgot about the fronts). I did manage to clear them in spite of the tube.

I laid out, trimmed up and cut out frame pieces for the engine cowlings.

I Hysol'd them into place all as one piece and will cut them down the center later... maybe.

I'm also considering keeping it all as one piece (including an exhaust pipe) and would have the whole assembly screw or magnet into place so that it could be removed for access to the tail area.

The gap down the center bottom between the cowlings will be taken care of later as well.

I'm still debating the pros and cons of functional cowling doors.

Also decided to keep the tail boom removable. Easier to go permanent than the other way around. Using four M2.5 screws, which should be discreet yet robust.

TEPT 89:30

Chapter 20: Gluing Up the Struts and Skids
Chapter 20: Gluing Up the Struts and SkidsChapter 20: Gluing Up the Struts and SkidsChapter 20: Gluing Up the Struts and SkidsChapter 20: Gluing Up the Struts and Skids
How People Feel About Chapter 20
Signing in takes just a code.Sign In to Comment